Successful completion of the revamping works for TIGF

Modernisation 2016 TIGF Fives Nordon-FIVES

Fives Nordon has successfully completed the modification of the Landiras switching station in France. The project consisted of installing 2 scraper stations to enable inspections of a 400 mm diameter pipe using a piston equipped with instruments and wiring the circuits to preserve the gas links.

This contract, that was won for the 11th year following a tough call to tender, gave Fives Nordon yet another opportunity to demonstrate its expertise in this type of work.

Fives Nordon was responsible for the design, preparation, prefabrication and on-site installation.

After 16 weeks of on-site work, the order was delivered, on time and fully compliant.